KLS solar powerplant

Project statistics
1,7

MWp

installed capacity

CO2 emissions reduced by

890

tons

annually

Situation before the contract

 

KLS Ljubno is a leading company in the production of toothed rings, signal rings and mass rings for engine flywheels of passenger cars, trucks and work machines, as well as industrial rings for various industrial use with a strong reputation among automotive customers and suppliers worldwide located in the Savinja Valley.

Resalta Solutions

 

Resalta has implemented photovoltaic power plant projects for KLS Ljubno with total power of 1700 kWp and with an environmental impact reduced by 890 tons of CO2 emissions avoided annually​

Photovoltaic power plant in Ljubno, was built in 2022.

Želite li vidjeti još?

Preuzmite naše studije projekata.

Uvjeti.

Pretplatom na naš newsletter pristajete primati e-mail poruke od Resalta d.o.o. Cilj našeg newslettera je informiranje posjetitelja Internet stranice, partnera, klijenata i opće javnosti o radu Resalte, njihovim novim projektima, razvoju događaja, predstojećim događajima te vijestima o energetskoj učinkovitosti i obnovljivim izvorima energije. Učestalost slanja newslettera bit će najviše mjesečna, uz moguće iznimke za neplanirane ali važne vijesti. Zadržavamo isključivo pravo da izmijenimo ili prekinemo newsletter, u bilo koje vrijeme i bez prethodne obavijesti. Smatramo vašu privatnost ozbiljno i nikada nećemo komunicirati ili prodavati vaše podatke trećim stranama. Možete se odjaviti s newslettera u bilo kojem trenutku.