Topolšica Hotel & Spa - Slovenia

Project statistics

Reduction of heating costs by

54

%

Installation of cooling in hotel rooms

Installation of a parallel heating system

Situation before the contract and client requirements


The Topolšica hotel and spa operates year-long and has a constant demand for heat.

Its heating system was wasteful, obsolete and unreliable, with numerous fall-outs. In addition the hotel was subject to the high price of district heating, thus incurring considerable costs for a system that could not meet all its needs.

Resalta solution

Resalta installed a 1.1 MW heat pump (water/water) as the main heat source. 

A new 100kW chiller (water/water) was installed to provide cooling for 61 rooms with fan-coils, with the possibility of connecting the remaining 61 rooms to the same system.

The heat pump has increased the demand for underground water and in order to reduce the cost of additional drawing rights, an existing pool waste water recovery system was installed. The existing boiler room was reconstructed to retain the existing system as a back up for periods of peak demand.

Želite li vidjeti još?

Preuzmite naše studije projekata.

Uvjeti.

Pretplatom na naš newsletter pristajete primati e-mail poruke od Resalta d.o.o. Cilj našeg newslettera je informiranje posjetitelja Internet stranice, partnera, klijenata i opće javnosti o radu Resalte, njihovim novim projektima, razvoju događaja, predstojećim događajima te vijestima o energetskoj učinkovitosti i obnovljivim izvorima energije. Učestalost slanja newslettera bit će najviše mjesečna, uz moguće iznimke za neplanirane ali važne vijesti. Zadržavamo isključivo pravo da izmijenimo ili prekinemo newsletter, u bilo koje vrijeme i bez prethodne obavijesti. Smatramo vašu privatnost ozbiljno i nikada nećemo komunicirati ili prodavati vaše podatke trećim stranama. Možete se odjaviti s newslettera u bilo kojem trenutku.