Gorenje/CHP – Slovenia

Project statistics

Annual savings

60,000

517

t

reduction of CO2 emissions

Situation before the contract and client requirements

Gorenje’s facilities in Velenje were using natural gas cogeneration (CHP) units for heat energy supply with 880 kW of combined heat power and 654 kW of electrical power. 

The required heat was 31,420 MWh annually, with an estimated 4,000 annual operating hours of the CHP.

Resalta solution

Integration of the right size of cogeneration (CHP) on natural gas; 850 kW of electricity and 929 kW of thermal power.

Resalta monitors the system through Resalta‘s central control system (web access) in real time, operating and maintaining the plant, also selling heat and electricity to the client.

Želite li vidjeti još?

Preuzmite naše studije projekata.

Uvjeti.

Pretplatom na naš newsletter pristajete primati e-mail poruke od Resalta d.o.o. Cilj našeg newslettera je informiranje posjetitelja Internet stranice, partnera, klijenata i opće javnosti o radu Resalte, njihovim novim projektima, razvoju događaja, predstojećim događajima te vijestima o energetskoj učinkovitosti i obnovljivim izvorima energije. Učestalost slanja newslettera bit će najviše mjesečna, uz moguće iznimke za neplanirane ali važne vijesti. Zadržavamo isključivo pravo da izmijenimo ili prekinemo newsletter, u bilo koje vrijeme i bez prethodne obavijesti. Smatramo vašu privatnost ozbiljno i nikada nećemo komunicirati ili prodavati vaše podatke trećim stranama. Možete se odjaviti s newslettera u bilo kojem trenutku.